Windows downstairs - Ben finished his, Harris finished another I started last fall, David to return two oval windows sometime in August. Leaves one downstairs and five upstairs to complete.
Electrical - finishing details and arranging payment
Plaster - two more weeks with Ed, four days left with Brad. Brad is prepping the final bedroom this week, Ed is finishing second coat on girls room today and will start top coat today or tomorrow. Next week is top coat on final room and any remaining details.
HVAC - to schedule layout next week, install to start August 4th be completed by August 7th when we will have AIR CONDITIONING!
Floors - Harris to have subfloor in living room laid by Monday so Genia can install new oak. Sand, patch, trowel, seal of all remaining floors to begin Wednesday, August 13th
Then, we arrange to get all of our stuff from TROSA storage, move into our house, and await our daughter's arrival
Electrical - finishing details and arranging payment
Plaster - two more weeks with Ed, four days left with Brad. Brad is prepping the final bedroom this week, Ed is finishing second coat on girls room today and will start top coat today or tomorrow. Next week is top coat on final room and any remaining details.
HVAC - to schedule layout next week, install to start August 4th be completed by August 7th when we will have AIR CONDITIONING!
Floors - Harris to have subfloor in living room laid by Monday so Genia can install new oak. Sand, patch, trowel, seal of all remaining floors to begin Wednesday, August 13th
Then, we arrange to get all of our stuff from TROSA storage, move into our house, and await our daughter's arrival